FROM THE WSDOT:We're in the final stages of the project now and are scheduled to complete 20 perfect openings of the bridge tomorrow, Tuesday, June 2. These tests are required to show that the bridge meets the operational standards for providing a safe and reliable draw span.
When the tests are done, we'll have an extremely clear idea (hint, hint) on when the bridge will be ready for 16,000 vehicles that cross it daily.
Over the weekend, crews from contractor Kiewit-General and WSDOT completed the following operations:
• Pulled together or “tensioned” the majority of the pontoon UVWX/RST joint
• Started Truss and transition span expansion joints
• Continued electrical wire installation and connecting and final ballasting
• Completed bolting started final tensioning
The exact opening time is still unknown because the testing work is unpredictable. Even if the crews have 19 successful tests and then the draw span doesn’t work on the twentieth test, they must begin the testing sequence with a count of zero once again.
An update on draw span work and testing progress will be provided on Monday afternoon (We'll make certain of it).
After the bridge is open, WSDOT will continue to provide transportation services for the day the bridge opens and one day after to help travelers return to their normal commute. Drivers are encouraged to plan ahead by visiting www.HoodCanalBridge.com or by calling 1-877-595-4222.